The Canal Authority have provided in their Advisory A-04-2016 tentative dates for locks maintenance:

Feb 25 (10 hours) Gatun
May 4-6 (2.5 days) Miraflores
May 24-27 (4 days) Miraflores
Jun 15-17 (2.5 days) Miraflores
Jul 5-8 (4 days) Miraflores
Jul 26-29 (4 days) Pedro Miguel
Aug 17-19 (2.5 days) Gatun
Sep 7-9 (2.5 days) Gatun

During these periods some congestion anticipated and waiting times for non booked vessels expected to be minimum 72/96 hours. Demand for transit booking, as customary, will exceed the booking slots available. Bookings allocated as per Canal Authority customer weighted ranking. One slot available daily via the auction process.


 